Construction Progress Tracker
Skyline One Sentosa Construction Progress 2026
A dated construction tracker following Skyline One Sentosa from launch and redevelopment transition into active piling and foundation works.

Current Status at a Glance
Where Skyline One Sentosa stands now
The project has progressed from launch and site transition into active piling and foundation works. The latest independently recorded stage is consistent with recent site footage reviewed by LPI.
Project Progress Timeline
From launch to foundation works
Official launch / Grand Opening
Skyline (Eastside) One Sentosa officially entered its public launch phase at the project property gallery.
Redevelopment transition
TSLAW Land held the Plaza Sentosa Light Off Event, marking the site’s transition into the redevelopment phase.
Demolition & site clearing
Dated footage supplied to LPI shows excavators, remaining structures, demolition debris and active site-clearing works.
Main piling contractor appointed
TSLAW Land announced Soletanche Bachy as the main piling contractor and stated that piling works had commenced.
Piling & foundation works
Later footage shows substantial foundation-related machinery on site, while myBina records piling and foundation works with substructure activity underway.
Visual Construction Evidence
Dated project evidence


What Is Happening on Site Now
The project is in an identifiable foundation stage
myBina currently records Skyline One Sentosa as Construction — Piling & Foundation Works, with substructure works underway. Recent site footage reviewed by LPI is visually consistent with that stage.
Main Piling Contractor
Why the Soletanche Bachy appointment matters — and where the conclusion should stop
TSLAW Land announced on 15 June 2026 that Soletanche Bachy had been appointed as the main piling contractor for Skyline (Eastside) @ OneSentosa.
The developer’s announcement lists past involvement in major projects including Petronas Twin Towers, Marina Bay Sands, ION Orchard & The Orchard Residences, International Commerce Centre, Landmark 81 and TSLAW Tower.
Buyer Meaning
What the piling stage actually means for buyers
What it does mean
The project has moved beyond launch material and preliminary site activity into a physical construction stage that can be observed and tracked.
What it does not mean
It does not yet prove on-time completion, final build quality, rental performance, resale performance or future management quality.
Next Milestones to Watch
What should come after foundation works
Substructure completion
Completion of below-ground and foundation-related structural works.
Podium & superstructure
Visible above-ground structural progress through the podium and residential towers.
Façade, M&E & commissioning
Later-stage building envelope, services, testing and eventual handover preparation.
Design Context
Planned appearance — not current construction

LPI Buyer Context
Progress is useful evidence, but unit selection still matters more
The September 2026 evidence confirms an active construction stage. For a buyer, the more important long-term questions remain whether later milestones continue to progress, whether the completed product matches approved specifications, and whether the exact unit is defensible on price, layout, facing, parking and intended use.
For full project analysis, read the Skyline One Sentosa Review 2026.
Need help comparing units?
Ask Louis about Skyline One Sentosa
If you are comparing unit types, layouts, price, facing, parking or buyer fit, you can WhatsApp Louis for a buyer-focused discussion based on your own priorities.
Sources & Verification
How this tracker is verified
- TSLAW Land — Skyline (Eastside) One Sentosa Grand Opening, 21 July 2025
- TSLAW Land — Plaza Sentosa Light Off Event, 26 February 2026
- TSLAW Land — Soletanche Bachy appointed as main piling contractor, 15 June 2026
- myBina — Skyline One Sentosa construction record, last verified 21 September 2026
Last checked by LPI: 23 September 2026.